透過您的圖書館登入
IP:3.149.26.169
  • 期刊

捷運專案之協調需求與供給

Coordination Needs and Supply of Subway Projects

摘要


協調是營建工程成功的關鍵因子,惟工程雖付出協調時間與成本,成效卻不如預期。本研究探討施工專案的協調需求與供給,首先由理論導出工作的不確定性(U)與模糊性(E)造成協調需求,工程師運用不同的工作方式提供協調供給;然後選取10個捷運施工專案,使用專案性質與環境問卷以衡量U和E,並設計表格調查工程師不同協調方式的時間分配;最後分析協調方式供給如何滿足協調需求,以及與績效的關係。研究結果發現,專案績效與U和E的高低無關;研究案例所使用的九種協調方式中,視察花最多時間(23%),公文處理次之(20.5%),會議佔13%;績效佳專案之承包商就工作模糊性的高低,選擇適當口頭或書面協調方式。

並列摘要


Coordination has been regarded as a critical factor of construction projects, but it is usually not well understood. It is common that time and money are spent on coordination yet the performance is not as expected. This paper studies the coordination needs and supply of construction projects. First, coordination needs were derived from work uncertainty and equivocality (U and E), and supply was offered by different methods engineers use to coordinate. Then ten subway construction projects were investigated. A questionnaire was modified to quantify the project U and E, and a time sheet designed to collect contractor engineers' work time allocated in nine coordination methods. Finally, how actual coordination time distribution meets the needs and their relationships with performance were analyzed. The results indicate that the project performance is not related to the level of U and E. In the nine coordination methods of the studied projects, site visit takes up most time (23%), followed by correspondence (20.5%) and meetings (13%). Projects with good performance apply adequate oral or written coordination mainly based on work equivocality.

被引用紀錄


周奕漳(2014)。專案管理與系統思考在施工計畫問題解決之應用-以河川環境營造工程管理為例〔碩士論文,國立交通大學〕。華藝線上圖書館。https://doi.org/10.6842/NCTU.2014.00329
宋孟秦(2016)。專案集管理知識領域在「易淹水地區水患治理計畫」之應用〔碩士論文,逢甲大學〕。華藝線上圖書館。https://doi.org/10.6341/fcu.M0360926

延伸閱讀