電力系統併聯電抗器啟閉暫態研究

The Switching Transient Phenomena of the Power System with Shunt Reactors

指導教授 : 王瑋民
若您是本文的作者,可授權文章由華藝線上圖書館中協助推廣。

摘要


台灣地區地下電纜逐漸普及,為調整必v因數及抑制電壓,併聯電抗器之使用為必然之結果。台電公司並聯電抗器單組容量161kV已規劃為80Mvar並於95年元月在大潭電廠加入系統。並聯電抗器與斷路器組合時之啟閉操作會發生截流與再弧暫態現象,造成截流過電壓與再弧過電壓已為大家所熟知,其中最為嚴重的問題為發生多重再弧時之電壓級升現象,以及再弧時之高頻電流之啟斷對斷路器接觸子之傷害。 由於首次使用161kV、80Mvar之並聯電抗器於台電系統中,希望對於截流過電壓與再弧過電壓有更深一層的認識,並希望藉由本文之研究探討電感電流之啟斷暫態現象對並聯電抗器用斷路器之絕緣劣化與接觸子熔損影響度,並訂定其運轉維護週期。本研究針對大潭電廠之電抗器回路進行ATP模擬分析,雖然分析之結果與相關文獻所得結果十分接近,但斷路器之再弧與截流現象及電源側與負載側之系統結構、參數有密切關係,實無法完全模擬,此乃現行相關之國際試驗標準中仍無法明訂的原因。由於無效電力調度需求以致並聯電抗器用斷路器操作頻繁,操作啟斷時共振之高頻再弧電流使得斷路器之接觸子在操作數百次就有可能熔損,本文中對應用於並聯電抗器之斷路器維護項目與點檢週期提出建議。

關鍵字

暫態 電力系統 電抗器

並列摘要


To compensate line capacitance current and to stabilize voltage in long distance transmission lines and cable systems, shunt reactors to be used in Taipower systems. It is known that shunt reactor current interruption causes a current chopping surge and reignition surge etc., and also it follow by high frequency arc extinction. The most important problem concerning phenomena related to the interruptions may be multiple reignition and resulting in a voltage escalation. The 161kV, 80Mvar reactor is first used in Taipower system. Extensive studies have been pursued in much more understanding such phenomena. However, reignition high frequency phenomena are affected by the entire system structure from the power delivery side to the load side. Furthermore, actual system parameters are very complicated, and they has not been fully investigated on the high frequency model. In case of SF6 gas insulated switchgear, the decisive factors in electrical durability are contamination and wear of parts that exposed to arc, such as nozzle and contacts. Due to high operation and high frequency reignition current the electrical durability of some parts were affected severely by few hundreds operations. The extra inspection and maintenance work of the GIS applied in shunt reactor switching is needed.

參考文獻


[4] “IEEE application guide for shunt reactor switching” , C37.015-1993。
[6]H. Kawada, K. Goto, M. Hanamura, S. Yanabu, S. Nishiwaki, T. Ueda, Y. Murayama, “Switching surge of shunt reactor caused by SF6 circuit breaker operation”, IEEE Transactions on Power Delivery, Vol. PWRD-2, No. 4. October 1987, pp. 1124~1130.
[8]E.Zaima, S. Okabe, S. Nishiwaki, M.Ishikawa, T. Nakamoto, Y. Murayama, Y. kawaguchi, “Reignition surge at reactor current interruption in cable-system” , IEEE Transactions on Power Delivery, Vol. 5, No. 2, April 1990. pp. 947~954.
[9]S. Okabe, M. Kosakada, H. Toda, K. Suzuki, M. Ishikawa, “Investgations of multiple reignition phenomena and protection scheme of shunt reactor current interruption in GIS substation.”, IEEE Transactions on Power Delivery, Vol. 8, No. 1. January 1993. pp. 197~202。
[10]Z.Ma, C.A. Blis, A.R. Penfold, A.F.W. Harris, S.B. Tennakoon, “An Investigation of transient overvoltage generation when switching high voltage shunt reactor by SF6 circuit breaker”,IEEE Transactions on Power Delivery, Vol. 13, No. 2, April 1998. pp. 472~479。

被引用紀錄


黃建維(2008)。南科供電系統無效功率與電壓變動分析〔碩士論文,崑山科技大學〕。華藝線上圖書館。https://doi.org/10.6828/KSU.2008.00036