以作業基礎成本法計算因工期展延所生間接成本之研究

Study on Measuring Construction Dispute Compensation by ABC Approach

指導教授 : 謝定亞
若您是本文的作者,可授權文章由華藝線上圖書館中協助推廣。

摘要


面對「因工期展延導致間接成本支出的增加」,若遲延原因可完全歸責於業主,則承包商可提出索賠,實務上計算索賠常用的方法是「比例法」與「實支法」,這兩種方法雖都有其優點,但於間接成本的計算上,其結果卻都不符合實際情況,例如比例法計算迅速但不精確;而實支法精確但過於繁雜,且證明困難。 目前國外有一種源於製造業的「作業基礎成本法(Activity Based Costing, ABC)」,因特別強調作業消耗資源的真實情形(包括直接與間接成本),故可提供管理者準確分析後的產品真實成本;本研究即欲以ABC之精神與觀點,分析「因展延所生間接成本」的索賠,找出較符合實際情況的計算方法。 若承包商處於工期遲延可體諒可補償之情況下(Excusable and Compensable Delay),則本研究之ABC其適用範圍如下: 1. 「變更設計」後,產生新增工項(Extra Work),並直接導致工期展延與間接成本之增加,排除單純之數量增減(Additional Work)。 2. 因可歸責業主之「工率降低」,導致工期展延的爭議(業主未要求趕工)。 3. 因「其他甲方因素」導致工期展延之情況(例如遲延簽發開工通知與工程停工等)。

關鍵字

ABC 工期展延 間接成本 爭議索賠

並列摘要


Time burdens are almost always accompanied by increased costs. However, even an undisputed right by the contractor of entitlement to costs would be difficult to exercise unless those costs can be satisfactorily quantified and proven. The value of diligent recordkeeping cannot be over-stated and the method for quantifying the cost of delay is an imperative for most contractors. In practice, contractor’s delay claims against the owner have been pestered with unsatisfactory method of quantifying damages. Most common methods adopted by the courts include the “ratio” approach and the “actual disbursement” approach. Each of them possesses certain advantages over the other, yet none of them leads to realistic compensation. This work introduces an innovative method of cost accounting, namely Activity Based Costing (ABC), and investigates its potential into the realm of delay damages quantification. It is done by examining and comparing the reasoning in court rulings with a counterpart analysis by ABC. The result of the analysis is the basis for further inference. It is argued that by using ABC a contractor who presents a detailed breakdown of reasonable costs incurred during the delay period is a step closer to full and just recovery. The ABC method is useful for items which are conventionally difficult to prove and rule, such as salaries of the contractor’s officers performing general services at the home or branch offices, most capital expenses which cannot be allocated among jobs, or home office overhead which may be apportioned to a given project. It is suggested that a further development on Activity Based Management may be in need in order to provide useful assistance or information on cost categorization and management. Such services could be crucial if the contractor plans to undertake public works or other highly competed sectors.

參考文獻


4. 行政院公共工程委員會,「政府採購爭議處理事件案源及問題類型分析」,2004。
20. 郭麗華,「工程間接費用索賠計算方法之比較」,國立成功大學碩士論文,2005。
21. 戚淑芳,「工程爭議之有效管理」,國立成功大學碩士論文,2005。
27. 吳秉澄,「工程間接成本問題探討」,國立成功大學碩士論文,2002。
1. 王兆俊,「國際建築工程索賠案例詳解」,海洋出版社,2007。

被引用紀錄


沈育丞(2013)。以工程法律案例資料庫為基礎之主題地圖系統〔碩士論文,淡江大學〕。華藝線上圖書館。https://doi.org/10.6846/TKU.2013.00851
林惠中(2011)。工期展延爭議與求償之法院判決分析〔碩士論文,淡江大學〕。華藝線上圖書館。https://doi.org/10.6846/TKU.2011.01382
鄒欣志(2012)。以ABC成本法衡量流程改善績效之研究〔碩士論文,國立屏東科技大學〕。華藝線上圖書館。https://doi.org/10.6346/NPUST.2012.00013
簡育文(2011)。台灣森林生態系統多功能服務效益評估之研究〔碩士論文,國立臺灣大學〕。華藝線上圖書館。https://doi.org/10.6342/NTU.2011.10173
岳巧珺(2008)。公路設施養護管理程序建立及成本分析之研究-以IDEF方法建立鋪面養護作業程序〔碩士論文,國立中央大學〕。華藝線上圖書館。https://www.airitilibrary.com/Article/Detail?DocID=U0031-0207200917355025

延伸閱讀