Title

BOT專案收購保證與貸款保證之探討

Translated Titles

A Valuation of the Purchase Guarantee and Loan Guarantee for a BOT Project

Authors

張大成(Ta -Cheng Chang);周麗娟(Li-Chuan Chou);劉宛怡(Wan-Yi Liu)

Key Words

收購保證 ; 貸款保證 ; 實質選擇權 ; 興建營運移轉專案 ; purchase guarantee ; loan guarantee ; real option ; BOT

PublicationName

經濟論文叢刊

Volume or Term/Year and Month of Publication

32卷4期(2004 / 12 / 01)

Page #

447 - 481

Content Language

繁體中文

Chinese Abstract

基於BOT契約的複雜性,為克服傳統資本預算評估專案價值的缺點,本文結合NPV法則與實質選擇權分析法,探討台灣高速鐵路契約中,收購保證及貸款保證條款,對不同參與者的影響,同時據以評估該BOT專案之價值。結果發現:在不考慮政府保證條款下,該專案之靜態NPV為36億元;而如果考慮政府同時給予特許廠商收購保證與貸款銀行團貸款保證的情況下,則理論上應該向特許廠商收取2,520億元之費用,其中包括:2,124 億元的風險承擔費,226億元的放棄選擇權價值,與170億元的貸款保證價值;並向貸款銀行團收取10.5億元的保證費用。可是政府部門並沒有收取任何的費用,卻分別做了不同的保證承諾。另外我們亦發現同時考慮收購保證及放款保證,對特許廠商持續經營之效果,明顯地優於只考慮收購保證,因為前者的最適放棄經營邊界低於後者,可有效緩和廠商放棄經營的道德危機。

English Abstract

This paper integrates the net present value (NPV) and real option theories to value the projects, purchase guarantees and loan guarantees for the contract of the Taiwan High Speed Railway (THSR) Build-Operation-Transfer project. The total construction cost is NT$ 325.9 billion and the static NPV is NT$3.2 billion for the THSR. However, we found that the project value of NT$252 billion was augmented for the consortium by the government guarantees, which included an increment of NPV of NT$212.4 billion, the purchase guarantee value of NT$22.6 billion and the loan guarantee value at NT$17 billion. Also, the value of the loan guarantee is NT$ 1.05 billion for the syndicate bank. To be more specific, these guarantee covenants are equivalent to the authorities granting purchase guarantees and loan guarantees to the consortium and syndicate bank at no charge. Furthermore, we also show that the optimal abandonment boundary of purchasing with loan guarantees is lower than only with a purchase guarantee.

Topic Category 社會科學 > 經濟學
Reference
  1. Brennan, M. J.,E. S. Schwanz(1977).The value of American put options.Journal of Finance,32,449-462.
  2. Hull, J.(2003).Options, futures, and other derivatives.Prentice-Hall Press.
  3. Lee, C. E.,J. E. Finnerty,E. A. Norton(1997).Foundations of financial management.West Publishing Company.
  4. Mason, S. P.,C. Y. Baldwin(1988).Evaluation of government subsidies to large-scale energy projects: a contingent claims approach.Advances in Futures and Options Research,3,169-181.
  5. Merton, R. C.(1977).An analytic derivation of the cost of deposit insurance and loan guarantees.Journal of Banking and Finance,32,3-11.
  6. Merton, R. C.(1974).On the pricing of corporate debt: the risk structure of interest rates.Journal of Finance,29,141-183.
  7. Mody, A.(1996).EDI Development Studies.Washington, D.C.:World Bank.
  8. Myers, S. C.,S. Majd(1990).Abandonment value and project life.Advances in Futures and Options Research,4,1-21.
  9. Rose, S.(1998).Valuation of interacting real options in a toll road infrastructure project.Quarterly Review of Economics and Finance,38(Special),711-723.
  10. Schwanz, E. S.,M. Moon(2000).Rational pricing of internet companies.Financial Analysts Journal,56(3),62-75.
  11. Tiong, R. L, K.(1990).Comparative study of BOT projects.Journal of Management in Engineering,6(1),107-122.
  12. 高速鐵路工程局(1998)。台灣高鐵公司所提高速鐵路建設民間投資法令障礙彙整案相關報導。高速鐵路簡訊,34
  13. 張大成、賴景昌(2000)。BOT放棄價值的評估-以台灣高速鐵路為例。管理學報,17(3),441-460。
  14. 黃小玲(1998)。產險業資金運用於公共投資之研究-以高鐵BOT為例。逢甲大學保險學研究所。
  15. 雷章寶(1996)。高速鐵路運量預測之淺釋。產業金融,93,55-89。
  16. 劉憶如、王文宇、黃玉霖(1999)。BOT三贏策略。商鼎財經顧問。
Times Cited
  1. 羅文聖、馮正民、康照宗(2007)。不確定財務環境下之BOT計畫自償率與財務資源分配分析。管理與系統,14(3),359-386。
  2. 蔡汶靜,林左裕(2021)。租賃契約條件對商用不動產租金影響之研究。住宅學報,30(1),49-69。
  3. 馮正民、郭秋鷰、康照宗(2008)。BOT計畫特許契約之權利金負擔議題分析。管理與系統,15(4),645-664。
  4. 黃思綺、康照宗(2009)。BOT計畫之運量保證與權利金平衡機制之研究。財務金融學刊,17(2),111-137。
  5. 黃思綺、馮正民、康照宗(2004)。BOT計畫政府與特許公司之權利金模式。財務金融學刊,12(3),1-31。