以BIM技術提升竣工時程網圖效用之研究

EFFECTIVENESS IMPROVEMENT OF AS-BUILT SCHEDULE USING BUILDING INFORMATION MODELING

摘要


國內專案時程控制主要以規劃時程網圖為主,然而國外許多時程延遲分析方法則會輔以竣工時程網圖,因此如何建立竣工時程網圖並提升其效用是國內時程延遲分析應面對的問題。建築資訊模型(BIM)技術已被應用於不同的領域,其中透過BIM技術及4D模擬,提早發現施工可能問題以提升整體效益已陸續被提出與實證。為提升竣工時程網圖於釐清爭議問題之效用,本研究提出結合BIM技術與竣工時程網圖建置之作法,並以某大學增建工程為案例,測試提出作法之可行性。研究成果已證明BIM技術可提升竣工時程網圖之解讀,而其效用可用於協助時程有關爭議課題的責任釐清。

並列摘要


Construction practitioners in Taiwan commonly control their projects merely on as-planned schedule (baseline schedule) but as-built schedule is usually used in many advanced schedule delay analysis method in some countries. How to develop as-built schedule and improve its effectiveness plays a key role in improving analytical quality of schedule delay analysis. Building Information Modeling (BIM) technique has been quickly adopted in different application domains, in which using BIM and 4D simulation techniques have been proposed and implemented as well as achieving obvious benefits especially in identifying and solving construction sequence-related problems in advance. This study proposes an approach to integrate as-built schedules and BIM models to improve the effectiveness of using as-built schedule in identifying schedule-related dispute problems. Through a real construction project in a university, the proposed approach of integrating as-built schedules and BIM models has been examined. Research results provide a vehicle to understand as-built schedule with the aid of BIM models and further to identify possible liability in schedulerelated disputes.

被引用紀錄


陳佑怡(2014)。以多目標最佳化演算法找尋最適融資辦法之施工排程—以台灣營建工程為例〔碩士論文,國立臺灣大學〕。華藝線上圖書館。https://doi.org/10.6342/NTU.2014.00236
左正揚(2007)。科技廠房營建發包工程最適化模式之研究〔碩士論文,國立中央大學〕。華藝線上圖書館。https://www.airitilibrary.com/Article/Detail?DocID=U0031-0207200917344362

延伸閱讀