透過您的圖書館登入
IP:3.135.204.121
  • 學位論文

國道新建工程局仲裁案例判斷結果之探討

『The Preliminary Study On The Results Of Arbitration Cases For National Expressway Engineering Bureau』

指導教授 : 郭斯傑

摘要


國道高速公路建設工程具有經費龐大、施工期長、用地取得困難、工程施工技術複雜等特性,承攬廠商於施工履約期間與業主為爭取自身利益難免發生爭議、求償情事。在爭議、求償未符合承商認為合理的救濟或要求下,為解決爭議在目前制度下可經由協商和解、申請調解﹙調處﹚、仲裁、訴訟等程序獲致雙方可接受的結果。國道新建工程局與承攬廠商雙方合意經由仲裁解決爭議,當事人之一方便可提付仲裁,經由此一程序獲致雙方可接受的結果。 國工局自民國79年成立以迄共發生百餘起仲裁案例並已作成仲裁判斷確定,目前尚有20餘件等待仲裁或正在仲裁庭攻防之中。經筆者於蒐集並經過篩選得其中88個樣本,試圖利用SPSS程式(Statistical Package for the Social Science套裝軟體)作各工程處間的比較,包括發包金額、求償金額、仲裁判斷金額相互間虛無假設後以T-test了解其假設是否成立,其差異是否顯著,兩母群體之變異數是否相同,並分析比較各仲裁判斷案例的理賠率。 經過相關之交叉比對分析可得到不同的工程類別,不同的工程處以及發包金額的大小對理賠率的影響。 初步成果: 1. 北二高理賠率較高;隧道較橋樑工程為高。 2. 國工局仲裁案並不一定 “輸”。 3. 理賠率總平均約為31%,所以大於31%以上才算輸。 建議:將來國工局應該趨向於以行政院公共工程委員會調處為解決爭議主軸,建議不仿以31%為底限,超過則不接受調處。

並列摘要


Abstract Due to huge cost, long duration, work area problem, and complex construction methods, the expressway projects inevitably have many disputes between the contractors and the clients during construction. In the local system, when the agreements of dispute solution are not reached, they can go for conciliations, arbitrations, or lawsuits. According to the contract between The National Expressway Engineering Bureau (NEEB) and the contractor, if they both are pleased, either of them can call arbitration for any dispute. The NEEB has experienced over 100 cases of arbitration since 1990. More than 20 other cases are still proceeding right now. This study collected 88 samples among the arbitration cases mentioned above. The arbitrations in each engineering division of NEEB were compared. Using the software of Statistical Package for the Social Science (SPSS), this study checks nill hypothesis of bid prices, claim money amounts, and the final money amounts. The claim-compensation ratios of arbitration were analysis by T-test, significant level, and their variables. After cross comparison, claim-compensation ratios showed to be influent by different category of project, different engineering division, and different law office. The preliminary conclusions was 1. The claim-compensation ratio in Third Expressway project is higher than the other projects in NEEB. The tunnel projects are higher than the bridge projects. 2. The arbitrations in NEEB are not certainly lose. 3. The “lose” means if the claim-compensation ratio is higher than the average of 31%. This study recommends that NEEB choose conciliation in Public Construction Commission, Executive Yuan to be the first priority to solve their dispute. NEEB should accept the conciliation if the claim-compensation ratio is lower than 31%, or reject the conciliation if it is higher than 31%.

並列關鍵字

Arbitration Claim-compensation ratio T-test

參考文獻


9.曾惠斌(2003) 行政院公共工程委員會出版品
18.駱怡明(2006)國道履約爭議之探討-臺灣大學土研所碩士論文
20.行政院公共工程委員會(2006)-政府採購法令彙編
【參考文獻】
1.SPSS INC.(1988)SPSS BASE 13.0-Applications Guide Chicago:SPSS Inc

被引用紀錄


林聰能(2012)。臺灣公共工程履約爭議處理機制之法律經濟分析〔碩士論文,國立臺灣大學〕。華藝線上圖書館。https://doi.org/10.6342/NTU.2012.00472

延伸閱讀