透過您的圖書館登入
IP:3.145.16.23
  • 學位論文

二次變電所主變壓器停電時未切離負載下逕行所內轉供之暫態分析

Analysis of Transfer Switching Transients under Load Condition when the Main Transformer Out of Service in the Secondary Substation

指導教授 : 周至如 洪穎怡

摘要


本文以ATP/EMTP電磁暫態模擬程式,模擬一典型之11.4kV配電系統,在二次變電所主變壓器發生事故停電時,逕行投入連絡斷路器轉供瞬間之暫態突波電壓與電流響應,藉以評估電壓突波是否會對線路上或用戶的設備造成危害,以及衝擊電流是否會造成提供支援之主變壓器亦跳脫,而擴大事故停電範圍,並藉此評估當某一主變壓器於發生事故停電時,其他主變壓器容量剩餘裕度允許情況下,逕行投入連絡斷路器轉供之可行性,以提昇恢復供電效率,縮短停電時間。 經由評估結果將提出轉供之程序與配套措施,利用餘裕度指數判斷是否逕行投入連絡斷路器轉供,而為了快速判斷餘裕度是否允許,各變電所可依其負載特性訂定其「餘裕度指數」,只備用容量大於此指數,就可進行後續轉供之操作,不過對於較敏感的系統,本報告提出運轉策略是將饋線以其供電持續性區分成兩個群組,一為急迫性群組,另一為一般性群組,前者需要有高度的供電持續性,如其他主變壓器尚有足夠備用容量時,必須優先復電,其切換程序是先將一般性群組的饋線切離,再投入連絡斷路器,最後再依剩餘備用容量多寡,逐步對一般性群組復電,此可兼顧急迫性負載的快速復電及降低開關突波電壓電流之衝擊,以提昇整體系統的供電可靠度。

並列摘要


In this report, the transient behaviors of surge voltages and currents due to transfer switching when a main transformer in the secondary substation are analyzed by simulating a typical 11.4kV distribution system based on the package of alternative transient program / electromagnetic transient program(ATP/EMTP). The damages may be occurred on the equipments of feeders and customers are evaluated based on the analysis results of surge voltages and currents, and the affection of other main transformers for supporting services to trip out will be surveyed. Furthermore, the feasibility of transfer switching under load condition when other main transformers still have enough spare capacities in assessed. Finally, based on the assessment results, the suitable procedure and measures for implementing transfer switching under load condition are proposed, where an index namely spare capacity index(SCI)for a substation can be determined based on its load characteristics. For conventioned cases, if the spare capacity is larger than SCI, then rapid transfer switching can be implemented. For those sensitive systems, however, the feeders are categorized into two groups. For the sensitive systems, however, the feeders are categorized into two groups namely urgent group and normal group based on the requirement of service continuity. The feeders of urgent group need high service continuity such that they will be first restored to service if the other main transformers still have sufficient spare capacities. For this, the operation procedure is defined as that the feeders of normal group should be first opened when their main transformer out of service, then the tie breaker is closed for energizing the feeders of urgent group to service, after that, the feeders of normal group are energized gradually according to the amount of left spare capacities of other main transformers. Under such operation procedure, both of rapid restoration for urgent loads and reducing the impacts of switching surge voltages and currents are all considered for increasing the reliability of the whole system.

參考文獻


[8] NEMA CP1.1988, Shunt Capacitors.
[1] 電力系統運轉操作章則彙編,捌、配電系統操作準則,四、事故時之處理,台灣電力公司,民國94年10月。
[2] 葉紅,用戶用電特性分析,台灣電力公司訓練講義,民國96年3月。
[3] 配電技術手冊(四),地下配電線路設計,台灣電力公司,民國85年8月修訂。
[4] 張文恭,許炎豐,李坤賢,邱貿瑞,賴建宏,施明宏,蒲冠志,「配電饋線中性線電流偏高問題之探討與改善策略」,完成報告,台灣電力公司,民國91年。

被引用紀錄


黃洚函(2015)。董事會多樣性與審計品質之關聯性研究-以中國為例〔碩士論文,淡江大學〕。華藝線上圖書館。https://doi.org/10.6846/TKU.2015.00775
葉韋伶(2014)。影響醫療財團法人財務槓桿因素之探討〔碩士論文,中原大學〕。華藝線上圖書館。https://doi.org/10.6840/cycu201400281
張育甄(2013)。合夥會計師規模與裁決性應計數之關聯性〔碩士論文,中原大學〕。華藝線上圖書館。https://doi.org/10.6840/cycu201300751
江宗翰(2010)。非審計服務與審計品質〔碩士論文,中原大學〕。華藝線上圖書館。https://doi.org/10.6840/cycu201000347
林順濂(2009)。使用非晶質鐵心改善低電流比之套管型比流器精度之探討〔碩士論文,中原大學〕。華藝線上圖書館。https://doi.org/10.6840/cycu200900162

延伸閱讀