解決捷運工程施工界面問題之探討-以臺北捷運(CD550標)工程為例

The study of how to solving the construction interface problems on Mass Rapid Transportation engineering-Taipei Metro (CD550) project as example.

指導教授 : 林志棟
若您是本文的作者,可授權文章由華藝線上圖書館中協助推廣。

摘要


捷運工程是一個規模龐大複雜之系統工程,而且必須興建於人口、交通稠密的都會區,在未來仍有大量捷運工程繼續興建之前題下,如何提高捷運施工效率,降低捷運施工對社會成本的衝擊,是未來捷運工程管理的新思維。施工界面整合對大型捷運工程的進度影響甚鉅,因此本研究透過實際案例及問卷調查之分析,探討當前捷運施工之界面問題進而研擬解決對策,協助捷運施工團隊提昇對施工界面管理之效率。 解決當前捷運施工界面對工期產生之影響,本研究導出四點具體之策略: (1) 在契約執行過程,由業主與廠商共同成立界面管理專責單位。 (2) 未來捷運工程繼續採整合區段標模式辦理發包。 (3) 將土/機界面整合進度,納入契約整體時程網圖加以管控。 (4) 契約中明訂廠商應具備界面專責組織與人員素質。 透過本研究之結論,冀望未來參與捷運施工之團隊,在界面協調管理的作為上,必須於施工初期明確訂定共同之組織、機制、文件、人員,在同一個界面平台上共同管理,方能有效解決捷運施工界面之問題。

並列摘要


MRT is a system engineering of large scale and complexity which is to be constructed in the region of metropolitan of dense population and traffics. Lots of MRT projects are under their way to build in the near future, no doubt, all have to think over the fatal necessity to improve the efficiency of construction and decrease the impact to the community. The integration of construction interfaces will apparently affect the progress and quality of giant MRT projects. Grounding on this thought, this study approaches the problem of interfaces of MRT projects by utilizing case study and questionnaires, and provides the solution to help MRT teams out of difficulties and enhance the efficiency of interface management. This study concludes four solid strategies for solving construction interface problems which impact the schedule of contemporary MRT projects. 1) Suggest establishing a specific collaborating team formed by the client and the contractor which is responsible for interface management during performing the contract. 2) MRT projects of full system integration are still recommended for the future. 3) The integrated construction/SEM interface needs to be included in the schedule network. 4) The specific interface management team and the qualification of team members should be specified in the contract. In the light of the conclusion of this study, calls for a platform on which all the stakeholders follow the ahead stipulated organization, mechanism, document and personnel of interface coordination from early stage of construction phase. Then, effective solutions for MRT construction interface issues are clearly there.

參考文獻


7.張志鵬,「統包制度對國內營造廠經營策略影響之研究」,碩士論文,中央大學營建管理研究所,2006。
21.黃金田,「捷運軌道工程介面管理知識庫系統建構之研究」,博士論文,中央大學土木工程研究所,P2-3頁2008。
30.Newbern and Jerry Nolte 1999.”Engineering of Complex Systems: Understanding the Art Side Sys.Eng,2(3)1999(p181-186).
31.Browning,Tyson R.(1998)”Integrative Mechanisms forMultiteam Integration Findings from Five Case Studies”,in “Systems Engineering”,Volume 1 ,Issue2,Page108,Jon Wiley and Son,Inc,New York,N.,1998.
1.賴銘利,「界面作業群組化管理之實務運用」,碩士論文,交通大學,94年7月。

被引用紀錄


張圳鴻(2013)。建築工程施工階段土建與機電 介面管理實務應用之研究〔碩士論文,國立臺北科技大學〕。華藝線上圖書館。https://doi.org/10.6841/NTUT.2013.00556
蕭富慈(2012)。營建工程介面管理模式及系統建置之研究〔博士論文,國立臺北科技大學〕。華藝線上圖書館。https://doi.org/10.6841/NTUT.2012.00105
陳文淑(2010)。捷運工程界面風險探討〔碩士論文,國立臺北科技大學〕。華藝線上圖書館。https://doi.org/10.6841/NTUT.2010.00637
陳宏銘(2014)。營建專案工程設計界面整合流程探討及改善之研究-以汽電共生廠興建專案為例〔碩士論文,國立臺灣大學〕。華藝線上圖書館。https://doi.org/10.6342/NTU.2014.11191
謝永昌(2010)。捷運工程施工階段業主風險管理之探討〔碩士論文,國立臺灣大學〕。華藝線上圖書館。https://doi.org/10.6342/NTU.2010.01597

延伸閱讀